Eko sklad 2026 for apartment buildings: how to prepare a successful energy renovation
Eko sklad public call 128VSSRS26 combined a grant with an interest-free loan repayable from the reserve fund. The call closed on 21 August 2026. The information below explains the preparation of an energy renovation and does not mean that a new application can still be submitted under this call. In practice, however, the greatest difficulties often arise from inadequately prepared technical documentation rather than financing. Successful energy renovation therefore depends not only on choosing a contractor, but above all on preparing the necessary documentation in good time.What should a building manager arrange before an Eko sklad application?
Before obtaining contractor quotations, it is advisable to check:- whether existing drawings of the building are available,
- which measures the unit owners intend to carry out,
- whether PZI construction documentation is required,
- whether a bill of quantities needs to be prepared,
- whether professional construction supervision has been planned,
- whether the necessary unit owners’ consents are in place,
- whether the reserve-fund arrangements are suitable.
When is PZI construction documentation required?
For energy renovation of apartment buildings, PZI construction documentation is often required or advisable. This is particularly relevant to:- façade renovation,
- flat roof renovation,
- pitched roof renovation,
- more complex thermal-bridge details,
- high-rise buildings with additional fire-safety requirements.
Why is a good bill of quantities important?
A bill of quantities is the basis for obtaining contractor quotations. Quotations are often not comparable because one contractor includes work that another leaves out. A good bill of quantities must define, among other things:- the type and thickness of thermal insulation,
- finishing coats and other finish layers,
- sheet-metal and flashing work,
- fire barriers,
- finishing of window and door reveals,
- repairs to the substrate,
- junction and edge details,
- all associated work needed for complete execution.
Why is professional construction supervision important?
Construction supervision is more than an occasional site visit. The supervisor monitors whether work is carried out in accordance with the documentation, bill of quantities and technical requirements. For energy renovation, checks include:- the suitability of installed materials,
- insulation type and thickness,
- fire-barrier installation,
- the quality of finish layers,
- critical construction details,
- consistency between the completed work and the design.
What does the energy renovation preparation process involve?
The usual steps are:- reviewing the existing condition of a building,
- defining the scope of the measures,
- preparing the project documentation,
- preparing the bill of quantities,
- obtaining contractor quotations,
- decision-making by the unit owners,
- submitting the application to Eko sklad,
- carrying out the works,
- providing professional supervision,
- preparing the required evidence after completion of the investment.
What did the closed call 128VSSRS26 offer?
A loan under this call could not be obtained separately from the non-repayable grant. The loan had the following terms:- a 0% interest rate,
- a repayment period of 2 to 10 years,
- repayment from the reserve fund.
Common mistakes in energy renovation
In practice, common problems arise when contractor quotations are obtained without a suitable bill of quantities, the documentation does not reflect the actual building condition or works proceed without professional supervision. This can result in quotations that cannot be compared, additional work, delays and poor workmanship. Timely technical preparation can reduce many of these problems.How can Xplan help?
Xplan d.o.o. provides professional support in the preparation and implementation of apartment building energy renovation. We offer:- preparing PZI documentation,
- bills of quantities,
- technical support for building managers,
- review of contractor quotations,
- professional advice for unit owners,
- construction supervision.
Do you need help preparing a project?
Energy renovation of an apartment building is a long-term investment. Documentation, bills of quantities and supervision should therefore be arranged professionally and in good time. If you are preparing an Eko sklad application or planning renovation of an apartment building, contact us to review the options and prepare the technical information for a well-executed and transparent project. Xplan d.o.o. 📧 info@xplan.si 🌐 www.xplan.si
Content rating: 5/5 · ratings: 2