Status checked on 1 November 2026: open (originally published on 6 June 2025, with subsequent amendments; the conditions on Eko sklad’s official website apply) – applications for Eko sklad grants for façades and insulation are processed in order until the call closes.
In June 2025, Eko sklad published the new public call 124SUB-OBPO25 for grants for energy renovation of apartment buildings, providing support for façades and thermal insulation.
Which measures are funded (A–D)?
A new investment, not yet completed when the application is submitted, in the common parts of an older building (at least 3 individual units) in Slovenia:
A – thermal insulation of external walls, floors above outside air or walls in contact with the ground – Eko sklad façade grant
B – thermal insulation of flat or pitched roofs or ceilings below unheated spaces/attics – Eko sklad thermal insulation support
C – thermal insulation of ground floors or floors above unheated spaces/basements
D – heating system optimisation (thermostatic valves + hydraulic balancing)
An older building under the call: one of the grounds listed in point 1 of the call must be met. The building permit must have been issued before 1 July 2010; for a building permit issued for legalisation, the building must have been constructed before that date and the permit issued before the application is submitted. The call also specifies other grounds for demonstrating legal status. Investments in parts that were unheated before the work are not eligible.
How much support does Eko sklad offer for insulation (2025/2026)?
Grant amount for façade thermal insulation in 2025/2026 (VAT is not an eligible cost under any measure):
A (façades, walls in contact with the ground, floors above outside air): up to 30% of eligible costs, capped at 50 €/m² (up to 60 €/m² for high-rise buildings; a high-rise building as defined in TSG-1-001).
B (roofs and ceilings below attics): up to 30%, capped at 50 €/m² (flat roofs) or 25 €/m² (pitched roofs/ceilings below attics).
C (ground floors / floors above basements): up to 30%, capped at 25 €/m².
D (heating optimisation): 50% of eligible costs.
Recipients of social assistance or income support: up to 100% in proportion to their share of the investment (VAT is not an eligible cost).
TNP (Triglav National Park): the final grant may be increased by 25% if the building being renovated is within the specified TNP area and the applicant has permanent residence at the address of that investment, or, for a legal entity, its registered office there.
Technical conditions for a thermal insulation grant
Technical thresholds (λ/d) – what must be achieved:
A (façades/walls in contact with the ground/floors above outside air): λ/d ≤ 0.200 W/(m²K)
When adding insulation over existing insulation, use 0.045 W/(mK) for the existing λ and document its thickness with a photograph showing a measuring tape.B (roofs/ceilings): λ/d ≤ 0.140 W/(m²K) (existing insulation is not included in the ratio).
C (ground floors/floors above basements): λ/d ≤ 0.280 W/(m²K) (existing insulation is not included in the ratio).
Note on façades: the fire safety of an ETICS system must be determined according to the height, use and composition of the façade. High-rise buildings are subject to the specific requirements of TSG-1-001:2019, point 2.11.6. A single non-combustible strip does not, by itself, demonstrate compliance of the entire façade. Fire safety requirements apply independently of the grant.
When are PZI and construction supervision required?
Eko sklad insulation requirements:
PZI is mandatory for measures A (façades, walls in contact with the ground, floors above outside air), B (flat/pitched roofs) and D (heating) – even where the work may be classed as maintenance. It is also mandatory to arrange supervision under GZ-1. The application to Eko sklad must include only the part of the PZI specified in the current call instructions; the full PZI must be provided on request (deadline ≤ 15 days). The call text refers to Appendix 1B differently in two places, so check the current form or Eko sklad’s clarification before submission.
PZI is not mandatory for straightforward insulation of ceilings below attics (B) and ground floors/floors above basements (C).
PZI for A and B is also not mandatory where a building has ≤ 8 individual units (the measure must then cover the entire building, rather than only part of it).
Eligible applicants and special conditions
Eko sklad façade grants are available to natural and legal persons (including the public sector, except direct users of the state budget) who are co-owners of the common part or lessees with the owner’s express consent. Restrictions apply concerning blocked accounts, tax liabilities and de minimis rules for legal persons and sole traders (a total of up to €300,000 over the last three years for a single undertaking).
Completion and payment deadlines
Investment implementation: 15 months from the decision becoming final (+ up to 6 months for objective reasons).
Completion documentation: within 2 months after the implementation deadline.
Payment: subject to available funds, payment is expected within 60 days after receipt and verification of all required evidence that the investment is complete (normally to the contractor’s account; if already paid, to the reserve fund or the authorised representative’s account).
Investment items must not be removed for at least 3 years after payment.
Which attachments are required with the application?
Common requirements: the part of the PZI specified in the current call instructions, a quotation for the PZI and supervision, or an invoice with proof of payment for a PZI already prepared, a list of co-owners (Excel), the authorised representative’s declarations, photographs of existing conditions, and, for A/B/C, also the materials’ declarations of performance (λ); for D: a schedule of heat emitters, photographic evidence of the system and diagrams of preset settings. Detailed lists are provided in the public call text.
Why Xplan
The PZI and supervision required under this call demand a comprehensive approach: appropriate thermal build-ups, details (scale 1:10), fire barriers, flat roof drainage with emergency overflows, hydraulic balancing with a measurement report, and similar requirements. These are precisely the areas we cover at Xplan on larger multi-apartment building projects, with a focus on coordinated documentation and a complete application; Eko sklad may request further explanations or additional information (gallery).
Quick FAQ (common questions from building managers and unit owners)
Can we apply for only part of the façade?
For buildings with ≤ 8 individual units, measures A/B cannot cover only part of the building – the whole building must be included.
How do we demonstrate λ when adding façade insulation?
The existing layer is assessed using λ = 0.045 W/(mK) and a photograph showing the thickness of the existing insulation against a metric scale.
What is a ‘high-rise building’ (higher amount under A)?
A building where the floor of the highest storey that may be occupied by users is more than 22 m above the positioning/working area for firefighting vehicles (under TSG-1-001).
The application is normally submitted by the building manager or a jointly authorised representative of all eligible persons (if there is no building manager).
Sources and call documentation
Eko sklad – public call 124SUB-OBPO25 (status, forms and call PDF)
Official Gazette of the Republic of Slovenia, No. 41/2025 – publication of the call (original publication; the current text published by Eko sklad applies DOWNLOAD THE ORIGINAL PUBLICATION)
TSG-1-001:2019 Fire safety in buildings (definitions, fire barriers and high-rise buildings DOWNLOAD FILE)
CONSTRUCTION SUPERVISION of the works (link)